WORK ON WATERS. Year 2009

 

Work Party 18th January 2009.

15 members attended.

 

Considerable attention was given to the Ditch pond in preparation for the complete replacement of the four remaining swims with raised platforms, it is anticipated that this work will be carried out at beginning of April, should other scheduled work go as planned.

The replacement of the ground swims with raised platforms has come about due to the constant high levels of water in the pond which has made the swims virtually unfishable.

 The cost of materials to build the platforms is far less expensive than the overall expense and work involved in putting in a drain and then rebuilding the existing swims as they are at present.

The rear areas of the swims were opened and cleared of the overgrowth of vegetation and the telegraph pole sections previously used in the construction of the swims were removed and stacked for re use.

A large amount of heavily overgrown Willow and Hawthorn was cut back around the south and east banks to afford light and water movement as previously recommended, this was stacked for later burning.

Several Silver Birch trees were cut down at the Newby pond to afford easier access for a survey with a view to removal of further overgrown vegetation. (Survey by Brian Hodgson due 18/02/09)

A review was undertaken of the Carp pond swims which have all but been destroyed as a result of constant high water levels over the last two winters, in preparation for rebuilding work to hopefully start on the next work party. The sighting of a “water level control drain” was agreed near to the North West corner. Near to peg 2.

All the anticipated work for that day was completed.

 

***********************************

 

 

 

 

 

 

Work Party 15th February 2009

16 members attended.

 

Attending Members were split into two groups who then concentrated there efforts between the Carp pond and the main group.  

The group who attended to the Carp pond dug a trench for the positioning of the previously agreed “water level control drain”. A section of underground pipe was then installed and the trench backfilled.

This was successfully completed with no unforeseen problems arising.

With the installation of this pipe the maximum water level of the Carp pond can now be controlled as excess water will be allowed to spill rather than flood over the swims and cause further erosion and damage, as has been the case for the last two winters.

Further work was then carried out on the initial clearing of the frameworks/structures of the existing swims ready for work to commence on the total rebuilding of the swims.

The second unit continued working around the main group and Ditch pond concentrating mainly on the Ditch pond.

The previously cut Willow and Hawthorn was burned in a controlled manner at a burn site at the pond.

All the anticipated work for that day was completed.

 

***********************************

<<<< Wednesday 18th February 2009>>>>

Brian Hodgson, “Aquatic Management Services” in company with Club Members, Graham Ward, Paul Bryan, Ray Pousty, Gordon Phillips and Peter Pownall, attended at the ponds for the purpose of Dr Hodgson advising the club regarding what work he felt was required for the further improvement to the club waters.

The group attended all the ponds on the main group including the Ditch, Tench and Newby. A number of areas on all ponds were identified were there was a requirement for the clearance and cutting back of some dense overgrown vegetation including hawthorn bushes and willows and some small trees.

These were marked with a red spray and notes were also taken of locations of overgrowth.

Dr Hodgson will be attending on a separate date (3rd March 2009) to take further surveys of the ponds with regards to water depth, quality and aquatic life and to report if a previous applied lime treatment had improved the ponds overall conditioning.(awaiting this report)

***********************************

Work Party 1st March 2009

16 members attended.

 

The attending members again split between two locations, these again being the Carp pond and the main group of ponds.

Those who attended the Carp pond began on the considerable work to repair and rebuild the damaged swims (all of which require some considerable attention).

(washed away/undercut and unsafe)

The members who attended the main group of ponds, concentrated there efforts towards the work required to open up the aspects of the ponds, they began the cutting and clearing of the vegetation/bushes previously identified on the 18th February.(Survey)

It was decided to work through the ponds individually starting with the May/June ponds.

All the identified vegetation that was cut back was cleared out, stacked and then burned in a controlled manner at the burn site at the pond.

All the anticipated work for that day was completed.

 

***********************************

Work Party 15th March 2009

16 Members attended (including 2 Juniors)

 

The attending members again split between two locations, these again being the Carp pond and the main group of ponds.

Those who attended the Carp pond resumed the work to repair and rebuild the damaged swims.

Some of these members had also attended during the previous week on unscheduled dates to continue with the required repair work to the swims.  

The members who attended the main group of ponds, continued to concentrate there efforts into the work required to open up the aspects of the ponds, in the cutting and clearing of the vegetation previously identified on the survey undertaken on 18th February.

The team concentrated there efforts of this day on the Misty, Bream and Clover ponds.

Again all the vegetation that was cut back was cleared out, stacked and then burned in a controlled manner at the burn site at the pond.

The anticipated work on the ponds which was drawn up set for completion prior to June is now slightly ahead of schedule.

 All the anticipated work for that day was completed.

 

***********************************

 

 

Work Party 5th April 2009

13 Members Attended (including 2 Juniors)

 

The attending members attended to the listed work on Newby pond.

A Health and safety issue had been raised at the April Committee Meeting with regards to the condition of the pathway between swims 16 and 17 at the end of the canal section. In that it was sloping and too narrow.

Lack of suitable materials had hindered the work from being previously undertaken.

The group initially split into two at the pond with nine  members attending to the cutting and removal of the previously identified and marked overgrowth of vegetation and trees.(Survey 18th February).

The second group of four, including the two attending junior members, attended to the health and safety issue previously identified and to the reconstruction of the pathway between pegs 16 and 17.(end of canal section)

Metal Scaffold poles, previously pulled out and no longer required from the rebuilt swims on the Carp pond and sections of Telegraph poles recovered from the fronts of the swims on the Ditch pond were used to form a secure raised barrier along the worst affected section of the eroded pathway. The earth on the high side of the bank was then loosened and dug out and then redistributed to back fill against the sections of poles. This has resulted in a level pathway which is double in width to before reconstruction.

Further work is still required on two shorter sections of less damaged bank on the same section and the erection of a safety hand rail along this section of bank. This work is scheduled to be undertaken on the 19/04/09, if materials are available and time permits.

The two groups then joined for the final hour to remove two large overhanging trees from between swims 4 and 5.

With the assistance of a large chain/straps and a 4x4 vehicle they were successfully cut down and dragged clear of the water. The removal of the barber wire fence was required to facilitate this.

Some of the cut vegetation was burnt in a controlled manner at site and some previously cut vegetation was also burned at the Tench pond burn site.

The perimeter of the pond was secured with bush and tree branches to prevent the cattle from getting in around the pond.

All the anticipated work for that day was completed.

***********************************

Work Party 19th April 2009

14 Members Attended (including 2 Juniors)

 

The attending members continued the listed work on the Newby Pond.

There were still some of the previously felled Hawthorn bushes, Willow trees and other bushes that, due to time factors on the previous party and  also there requirement to use them to secure the perimeter from cattle and had been left where felled, were the first to be pulled clear and cut up.

Once the fire was started these were then stacked for burning. Work then commenced to cut and clear the previously “marked for clearance” trees and bushes around the pond. (still some remedial cutting back required)

New posts were driven in at the cleared area and approximately 30 feet of the barb wire fence, previously removed to afford access to the trees, was replaced, some further damaged sections were repaired.

The two main pathway access stiles were repaired.

One of the swims handrails was also repaired.

The Water Pump had been running throughout the work party in the Tench pond, in an effort to reduce the water level “reduced by 4 inches this time” so that the swims can be assessed and repaired. (a new overflow control drain is to be installed to prevent further problems with the raised water levels suffered over the last two winters)   

Mark Parry continued his sterling work in the planting of pond side and marginal aquatic vegetation around the ponds.

Unfortunately due to time factors the scheduled work on the pathway at the end of the canal section was not full completed, this also including the installation of handrails.

It is anticipated that this work will be completed by the end of the next two work parties.(prior to season opening)

***********************************

26th April 2008

Two members, including one junior attended the Newby Pond and built the Hand Rails (not constructed 19/04/09) along the section of previously reconstructed pathway at the end of the canal section.

Handrails were also built at this time on two separate identified swims.

One as required on number 17 swim, were two sections were erected and also on number 18 swim were part of the existing broken hand rail was used as a bottom rail down the length of the steps.( awaiting review of suitability by Heath & Safety Member)

***********************************

 

Work Party 3rd May 2009 (bank holiday weekend)

17 Members Attended including 2 juniors and 2 new members

 

The attending members split between two locations,

11 members made to the Stork pond to give the area its first strim and general cut back and clear up of the year. The pond has been a little neglected recently due to all the other work this year, having been directed to the main group of ponds and to the total re building of the swims on the Carp pond.

The attending members cleared around the swims and cut back some overgrowth of vegetation. Due however to overnight rain, it was decided to stack the cut material at the burn site ready for future burning once it has had some time to dry out. (further strimming and grass cutting required soon)

The remaining six members, including the two junior members, attended at the Ditch pond. Two of the four original, previously damaged and previously removed swims, were replaced with new raised wooden platforms.

The two new platforms still require some minor attention before they are complete, however, it is anticipated that this work and the building of the two remaining platforms, will be fully completed before the beginning of the season (June 1st)

The water pump was again run in the Tench pond and again a noticeable reduction to the water level was achieved buy the end of the work party.

The water level has now been sufficiently lowered so as to afford a brief survey as to the condition of some of the swims to be conducted.

The good news is, that damage to the swims appears not to be as bad as previously expected and although the water level still requires reducing some further eight to ten inches before work can fully commence to rebuild the swims, the previously anticipated work required will now, hopefully, not be as extensive as was first thought and we will hopefully be able to complete the work sooner than expected. A full assessment will still need to be carried out once the water reaches the desired level.

It is anticipated that the refurbishment of the swims on the Tench pond will now commence, either on the June 21st or July 19th Work Parties. Some work will be carried out to clear vegetation and open up swims on the work party scheduled for 17th May. (some swims are at present fishable)

The new Water Level control drain will be placed to run across the meadow and allowed to spill into the natural drainage ditch from the south east corner of the Tench pond. This will be laid with the assistance of a digger (due to depth and distance) once correct water levels are reached.

 

 

It is now anticipated that the new Water Level control drain will be installed on the June Work Party date (21st June). The JCB has been provisionally booked for this date.

***********************************